Name of the Project | Irrigation Management Improvement Project (IMIP) for Muhuri Irrigation Project |
---|---|
Sponsoring Ministry | Ministry of Water Resources |
Executing Agency | Bangladesh Water Development Board (BWDB) |
Financing of the Project | Asian Development Bank (ADB); Loan No. 3135-BAN (SF) & GoB |
Approval Status | The project was approved by ECNEC on 17-06-2014 |
The objective of the Project
The overall objectives of the project are:
- To reduce poverty by enhancing food security through increased yield of crops.
- The IMIP will address Muhuri Irrigation Project (MIP) to be implemented in 2014-2015 to 2018-2019.
- This project will also undertake feasibility study of (i) Ganges-Kobadak Irrigation Project (GKIP), dry season irrigated area of about 96,000 ha; and (ii)Teesta Barrage Project (TBP), dry season irrigation area about 60,000 ha; for the formulation of Development Project Proposal (DPP) later on under the financial assistance of the Asian Development Bank (ADB).
- The Project targets the rehabilitation of the water infrastructures of the MIP for a gross 60,258 ha area in Purshuram, Phulgazi, Chhagyal Niayyia, Feni Sadar, and Sonagazi Upazila of Feni District and Mirsarai Upazila of Chittagong District. The net cultivable area of the project is 28,663 ha; net irrigated area of 17,900 ha (with surface water and groundwater) in the pre-project condition; but the “With-Project” irrigated area was 23,600 ha (including Kahua River Area). This irrigated area was reduced to around 11,000 ha due to siltation and lack of maintenance. In the current ongoing IMIP project, the target is to increase this irrigated area up to 17,900 ha with modernization facilities.
- The two projects targeted for feasibility study under this project as mentioned above are located respectively in the South Western Region (GKIP) and in the North West Region (TBP). The GKIP covers areas in the Districts of Kushtia, Jhenaidah, Chuadanga, and Magura and the TBP covers areas in the Districts of Rangpur, Nilphamari, and Dinajpur.
The specific objectives of the project (MIP):
- Sustainable operation and maintenance of Muhuri Irrigation Project (MIP) through rehabilitation of the irrigation infrastructures, improvement of irrigation management through innovative approaches for modernization and cost recovery in full for the Level 2 (Secondary canal systems) and the Level 3 (framers’ canal system) infrastructures O&M while the Executing agency will carry out O&M of the Level 1 (Embankment, regulators and primary canal system/rivers) of the MIP with a contribution by the GoB.
- Increase sustainability of the development of the MIP through effective community participation.
- Repulse floods and use water resources effectively.
- Increase farmers’ income and strength livelihood through improved productivity.
Project Area
Division | District | Upazila |
Chittagong | Feni | Purshuram, Phulgazi, Chhagal Naiya, Feni Sadar, and Sonagazi. |
Chittagong | Chittagong | Mirsarai |
Project Cost
Fund | Original DPP | 1st Revision DPP | 2nd Revision DPP |
RPA | Tk. 36,800.0 lakh | Tk. 37,774.44 lakh | Tk 47,600 lakh |
GOB | Tk. 8,935.72 lakh | Tk. 8,935.72 lakh | Tk 10414.00 lakh |
Total | Tk. 45,735.72 lakh | Tk. 46,710.16 lakh | 58014.00 lakh Taka |
ADB Loan | USD 46.00 Million | USD 46.00 Million | USD 59.50 Million |
Project Period
Original: July 2014 to June 2019
1st Revised: upto June 2020
2nd Revised: upto June,2022
Loan Effectiveness: 17 Sept 2014
Main Component of 2nd RDPP
Items | Quantity | RDPP Cost (Lakh taka) |
Rehabilitation of Coastal Embankment | 17.75 Km | 544.00 |
Rehabilitation of Sluices | 4 Nos. | 183.15 |
Construction of New Sluices | 2 Nos. | 461.64 |
Rehabilitation of Water Control Structure | 3 Nos. | 224.23 |
Construction of Water Control Structure | 5 Nos. | 895.97 |
Re-excavation of Khals | 405 Km | 4112.84 |
Farmer Canal System (For Irrigation ) – Burried uPVC pipeline: 850 Km. – Electrical Low lift pump: 890 nos- Pre-paid meter: Approx. 860 nos |
18000 ha | 21700.00 |
Upgrading of Electricity Distribution System (For Irrigation of 18000 ha area) | 210 Km including 1 Substation | 5600.00 |
Scheme Operation and Maintenance | 1 Item | 2000.00 |
Package wise Progress:
Package No. |
Description of Procurement Package as per RDPP WORKS |
Unit |
Quantity |
Contract Price |
(%) of the Progress |
Cumulative Financial Progress Upto Dec, 2020 |
Remarks |
CW-01 |
Rehabilitation of Coastal Embankment + Re-excavation of Khals Group 1+Re-excavation of Khals Group2 |
Km |
Embk. 17.75 Km, Khal 202.00 Km |
2355.67 |
81.00% |
1832.04 |
Completed |
CW-02 |
Re-excavation of Khals Group3 + Re-excavation of Khals Group 4. |
Km |
Khal 203.00 Km |
2301.17 |
92.00% |
2069.10 |
Completed |
CW-03 |
Farmers’ Distribution system, Stage 1: Area 1830 ha: Pipeline |
Ha |
1830 |
1736.41 |
93.00% |
1406.20 |
|
CW-04 |
Upgrading of Electrical distribution lines for 18000 ha |
No/ Km |
1 No /210 Km |
4436.00 |
54.00% |
2050.77 |
|
CW-05 |
Farmers’ distribution, pumps and prepaid meters: Stage 2: Area 5070 ha |
Ha |
5070 |
5741.40 |
17.00% |
1218.99 |
|
CW-06 |
Farmers’ distribution, pumps and prepaid meters: Stage 3: Area 5,400 ha |
Ha |
5400 |
6577.25 |
11.00% |
1055.51 |
|
CW-07 |
Farmers’ distribution, pumps and prepaid meters: Stage 4: Area 5,700 ha |
Ha |
5700 |
7491.42 |
10.00% |
2339.5 |
|
CW-08A |
Construction of new Water Control Structures, sluice; rehabilitation of structures, Sluice |
Nos |
11 |
1265.55 |
95.00% |
1108.31 |
Completed |
CW-08B |
Repair of BWDB Buildings of Feni, BWDB |
As per list in DFSR |
– |
145.97 |
100.00% |
143.81 |
Completed |
CS-01 |
Project Management & Design Consultants (PMDC) |
Item |
L.S |
5887.36 |
81.00% |
4540.52 |
|
CS-02 |
Irrigation Management Operator (IMO) |
Item |
L.S |
5074.00 |
63.00% |
3150.91 |
|
Cumulative Expenditure up to 31st December, 2020:
- GoB = Tk 3509.17 lakh
- PA = Tk. 17465.45 lakh
- Total = Tk. 20974.62 lakh
- Physical Progress: – 45.34%
Tasks of the PMDC Consultants
- Design hydraulic structures of MIP
- Prepare feasibility studies, detailed engineering designs and bidding documents of civil works of GKIP and TBP
- Prepare “follow on” investment project of GKIP & TBP
- Support and supervise the Irrigation Management Operator (C-IMO) of MIP.
- Plan and
- implement training for the PMU on ADB’s lending modality, assist public-private-partnership (PPP) initiative for irrigation projects
- Prepare review of the performance of the C-IMO of the MIP
Tasks of the IMO Consultancy Services
Activity 1: Establishment of efficient and sustainable MOM of Level 2 and 3 infrastructure
Activity 2: Construction supervision of investment works (coastal embankment, structures, khal excavation, pipe distribution, electrification).
Activity 3: Participatory design of the Level 3 distribution systems 15,000 ha irrigable area
Activity 4: Agricultural support services, pilot supplementary cost recovery activities, and implementation of training and awareness programmes-(provisional sums).